Time Effectiveness and Cost Efficiency with Crashing Method, Overlapping, and Combined in Los Development Project Ngadiluwih Market
DOI:
https://doi.org/10.31004/joecy.v6i1.9577Keywords:
Algorithm Culture, Digital Da'wah, Media Ecosystem, Qur'anic Interpretation, Social MediaAbstract
Background: The Ngadiluwih Market Los construction project in Kediri is experiencing potential delays with a normal duration of 210 days and a RAB of Rp12.55 billion, requiring optimization of time and costs through crashing, overlapping, and a combination of these to meet the final target of 2025. Objective: To analyze the effectiveness of the crashing method (overtime and additional labor/equipment), overlapping, and their combination using Microsoft Project. Research Type and Method: Descriptive quantitative through literature studies, field observations, and critical path analysis. Population and Sample: All project activities (210 days); purposive sampling of critical paths such as excavation, foundation, and steel structure based on the RAB and schedule of consultant CV. DAWS Architects. Analysis Instruments and Techniques: Microsoft Project and Excel for cost slope, crashing (additional human resources/tools), overlapping (changing FS relationship to SS/FF with lag), and cost/duration comparison. Results: The combined crashing method added labor/equipment and overlapping was the most optimal with a duration of 137 days (saving 73 days) and cost efficiency of IDR 218 million (ratio 0.983). Conclusion: The combined crashing-overlapping approach is superior for accelerating traditional market construction projects, with recommendations for adoption in similar PUPR projects for maximum
References
Abrar, H., & Husen, I. (2010). Project management (Revised edition). Andi.
El Unas, S., Hasyim, MH, & Negara, KP (2014). Anticipating project delays using the what if method with Microsoft Project. Civil Engineering, 8(3), 192–197.
Huda, MN (2018). Optimizing facilities and infrastructure to improve student learning achievement. Ta'dibi: Journal of Islamic Education Management, 6(2), 51–69. (Used as a reference for the optimization concept)
Husen, A. (2009). Project management. Andi.
Iswahyudi, MS, Prasetyo, A., & Nugroho, R. (2023). Marketing Management: Effective Strategies and Practices. PT Sonpedia Publishing Indonesia. (Used for the context of economic benefits and efficiency)
Majid, A., & Ariwibowo, CV (2017). Optimizing time and costs in the construction of the Class II B Open Prison in Kendal, Kendal Regency (Thesis). Faculty of Engineering, Sultan Agung Islamic University.
Mulia, NH (2022). Cost and time analysis of the Kudus Regional DPRD Fraction Building construction project (Thesis). Sultan Agung Islamic University, Semarang.
Prastika, NR, & Rosyada, K. (2024). Time effectiveness and cost efficiency in the Weleri 1 Kendal Market project (Thesis). Sultan Agung Islamic University, Semarang.
Rangkuti, M. (2023). Construction management: Definition, aspects, functions, and objectives. Faculty of Engineering, Muhammadiyah University of North Sumatra.https://fatek.umsu.ac.id/manajemen-konstruksi-pengertian- Aspek-fungsi-dan-tujuan
Saputro, NH, & Utomo, YW (2025). Analysis of planning the time effectiveness and cost efficiency of the construction project for the library and archives service facility building in Salatiga City (Thesis). Sultan Agung Islamic University, Semarang.
Shafira, FN, & Pertiwi, HP (2020). Analysis of time and cost acceleration planning for the Promasan Bridge construction project in Salatiga (Thesis). Sultan Agung Islamic University, Semarang.
Siregar, AC, & Iffiginia, I. (2019). The use of the Critical Path Method (CPM) for evaluating project implementation time and costs. Engineering: Journal of Science and Technology, 15(2), 102–111.
Soeharto, I. (1997). Project management: From conceptual to operational. Erlangga.
Sugiyanto, I., & Mt, M. (2020). Project control management. Scopindo Media Pustaka.
Sunarta, DA, & Darwis, A. (2023). Introduction to research methodology. Tohar Media.
Susanto, RY (2018). The potential of the traditional starfruit market for the community around Lowokwaru District, Malang City. Journal of Management and Accounting References, 6(2), 39–47.
Umar, MA (2021). Time and cost analysis using crashing, overlapping, and combined crashing–overlapping methods (Case study: Bendo Advanced Dam Construction Project, Ponorogo Regency) (Thesis). Sultan Agung Islamic University.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2026 Eni Nur Safitri, Inge Anggitasari, Susilowati Susilowati, Olvi Pamadya Utaya K

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.